The first hydrostatic
barrier, consisting of a deep soil mix and steel sheet piling, lies beneath and
around the 9.1 acres along South
Miami Avenue, between 6th and 8th Street. This barrier allows for the
planned excavation for construction of 2 levels of underground parking beneath
the future Brickell City Center. Transforming the center of Miami's financial district will be 5.4
million square feet of office, residential, hotel, retail, and entertainment
space.
To properly begin
construction, developers had to insure a dry excavation. Due to a high
groundwater table and the porous nature of this region a specifically
engineered solution for this $1 billion project was developed. In July 2012,
the beginning stages of the hydrostatic barrier were started. Once completed,
the barrier would be applied to more than 3 city blocks before construction of
the 2-level underground parking garage could begin. The massive underground
parking garage, which spans over 7 acres underneath the total 9.1 acre
property, was completed in February of 2014.
Above the parking
garage will not only sit the shopping center, office space, hotel and
apartments, but a 131,000+ square foot wellness center, over 800 condominiums
and 2,400 parking spaces. To support architecture on such a grand scale, 100,000
tons of bulk cement was used to create deep soil mix plugs. These plugs would
hold the sheet piles, preventing water from flowing up alongside the sheet piling
during extensive excavation. After these plugs were set, cast piles for the
future structure were installed to depths in excess of 100 feet.
In order to accommodate
the new building footprint, relocation of existing utilities had to take place.
Some existing utilities had to be rerouted while others had to be taken out of
service completely. The amount of coordination involved to complete this
project was tremendous. When dealing
with contractors, subcontractors, consultants, project managers and so forth;
decisions had to be made in hours and days, not weeks. It all just goes to show
how an accelerated schedule can have effects on the need to get certain jobs
completed by a set deadline.
This transformation of
downtown is being done in 2 phases. The first phase is scheduled to be complete
by the end of 2015. With such an aggressive timetable in place, crews have had
to remain focused to keep on pace. Phase 2 is expected to initiate sometime in
2018. Upon completion, an engineering milestone will be responsible for the
vast architecture genius that has taken place in downtown Miami.
No comments:
Post a Comment